MoPNG has issued component-wise operational guidelines for the GOBARdhan Scheme covering Compressed Biogas (CBG). This page translates the official Office Memorandum into a bankability-focused briefing for developers, lenders and EPC teams — offtake, pricing, capital assistance, pipelines, credit guarantee and ecosystem support — with figures taken only from the OM.
Citation: MoPNG OM cover memorandum · Scheme period FY 2026-27 to FY 2035-36
GOBARdhan is a coordinated CBG ecosystem framework — not only a subsidy notice. The OM encloses six operational components. The Scheme was approved on 6 August 2026; these guidelines operationalise it.
Firm demand via CGD and trunk-pipeline routes, CBO trajectory, and tripartite contracts with GAIL as Synchro Operator.
Administered CBG Price (ACP) paid by the Synchro Operator, plus Government affordability support to keep retail tariffs workable.
Capacity-linked plant grants and separate machinery/FOM support, milestone- and PLF-linked — capped per project and group.
Financial assistance for CGD links and GAIL-operated cluster trunk connectivity subject to distance and utilisation rules.
NCGTC-managed CGSCBG fund providing partial guarantee cover for eligible MSME greenfield CBG term loans.
District competition awards plus selective grants for equipment, yield, FOM/LFOM value-add and ecosystem gaps.
Sources: OM cover ¶1–2; Comp I §2.3.3; Comp II §2.6; Comp III §2.3–2.6
Business meaning: replace “reasonable endeavour” uncertainty with firm contractual offtake — while adding producer-side quality, nomination and supply obligations.
CBO may be amended by MoPNG as required.
Sources: Comp I §§2.3, 3.2–3.9, 4–8; Appendix I TOP/SOP & enforcement
Business meaning: clearer revenue modelling via Administered CBG Price — while accepting that ACP can be reviewed, and by-product realisation is part of the price design.
Sources: Comp II §§2.4–2.6, 3.2–3.3, 4.1–4.3
Business meaning: non-dilutive, capacity-linked support — but it is two sub-components, milestone-gated, and capped. It is not automatic day-one equity.
| Category | Assistance | Key conditions |
|---|---|---|
| Sub-Component I — Plant core (greenfield) | ₹1.25 Cr / TPD | Eligible greenfield CBG establishment |
| Brownfield expansion | 50% of applicable Clause 4.1 rate | Only additional capacity from fresh CAPEX |
| Special Category areas | +20% over Clause 4.1 | NE States & Sikkim; Uttarakhand; Himachal Pradesh; UTs of J&K, Ladakh, Lakshadweep, A&N |
| Existing biogas → CBG upgrade | ₹0.60 Cr / TPD | Max ₹5 Cr per project |
| Sub-Component II — Machinery & FOM | 50% of eligible cost (max ₹0.75 Cr / TPD) | Feedstock aggregation & organic manure value-addition machinery (eligible list) |
| Project aggregate cap | ₹30 Cr / project | Across both CA sub-components |
| Group / entity cap | ₹500 Cr / financial year | Entity and subsidiaries (as defined in guidelines) |
| Application window | Open till 31.12.2030 | |
Sources: Comp III §§2.3–2.4, 3.10, 4.1–4.6, 5.2, 7.3; application window §4.6.1
Business meaning: reduce evacuation risk with co-funded last-mile / cluster lines — distance-capped and utilisation-verified.
Sources: Comp IV §§3.1, 3.10, 4.1.3–4.1.8, 5.1–5.3
Business meaning: make MSME CBG term loans more bankable via partial sovereign-backed guarantee — it is not a grant, waiver or Government repayment of your loan.
Sources: Comp V §§1, 5–9, 11–12, 14
Business meaning: selective ecosystem money — district competition plus enablement grants for technology, yield and by-product value chains. Application does not create entitlement.
Sources: Comp VI §§3.1–3.4, 4.6, 5.2–5.4, 6.2
Sequencing implied by the guidelines — not a substitute for statutory calendars or your DPR.
Quantity, composition, seasonality, radius, landed cost and contracts. Confirm MSW/sewage share stays below exclusion thresholds if seeking CA/CG.
CGD mapping vs cascade vs trunk cluster feasibility; quality specs for the chosen route (PNGRB codes and/or IS 16087:2025).
Obtain project registration and Plant ID — required for offtake, ACP, CA, pipeline FA and credit guarantee paths.
Technology, mass balance, CAPEX/OPEX, ACP revenue case with revision sensitivity, DSCR, risk and PLF pathway for tranche 3.
Tripartite firm offtake (not only reasonable-endeavour); CTE/PESO and other clearances needed for CA milestones.
Promoter equity + bank debt; CGSCBG via Jan Samarth if MSME greenfield; plan working capital and BG for CA tranches — do not treat CA as day-one equity.
SCADA, online GC/MS, interlocks, geo-tagged uploads and MoPNG data access designed into the plant — not bolted on later.
Document first sale for tranche 2; run continuous months and 24-hour PLF for tranche 3; keep CA/BAM self-certifications accurate.
₹1.25 Cr/TPD (plant) and up to ₹0.75 Cr/TPD (machinery) are separate, capped, eligibility- and milestone-linked. Aggregate CA cannot exceed ₹30 Cr per project.
Initial ACP is ₹2,110/MMBTU, but PAB may review/revise; PPAC notifies. Horizon runs at least to 31 March 2036 — not a promise of zero revision.
CGSCBG covers the lender’s risk partially. The borrower remains liable. Greenfield MSME only; many brownfield / MSW cases are excluded.
Guidelines say aggregate capacity is preferably 20 TPD or higher, with at least two plants of ≥2 TPD each — not a hard single-number entitlement.
This OM references IS 16087:2025 for biomethane specification (with applicable PNGRB access codes by route).
₹12.5 + ₹7.5 = ₹20 Cr is illustrative maximum eligibility arithmetic before the ₹30 Cr cap — not a guaranteed disbursement schedule.
| Item | Verified point |
|---|---|
| Total outlay | ₹23,731 crore (FY 2026-27 to FY 2035-36) |
| Initial ACP | ₹2,110/MMBTU ≈ ₹98/kg at 95% CH₄, excl. taxes & compression |
| Affordability support | Up to ₹10/kg (₹215.31/MMBTU) to Synchro Operator |
| CBO trajectory | 3% / 4% / 5% from FY27 / FY28 / FY29+ |
| TOP / SOP | Year 2+: up to 90% ANQ / 50% ACQ; Year 1 relief |
| Greenfield CA (plant) | ₹1.25 Cr/TPD |
| Machinery CA | 50% eligible cost; max ₹0.75 Cr/TPD |
| Biogas→CBG upgrade | ₹0.60 Cr/TPD; max ₹5 Cr/project |
| CA project / group caps | ₹30 Cr/project; ₹500 Cr/FY (entity & subsidiaries) |
| Pipeline FA | 50%; Steel ≤₹50 L/km; MDPE ≤₹7.5 L/km; ≤75 km |
| CGSCBG | ₹625 Cr fund; 85%; ₹20 Cr / ₹25 Cr ceilings; to 31.12.2030 or ₹15,000 Cr loans |
| Challenge Fund | ₹500 Cr (FY26–27 to FY30–31); district ₹5 Cr / ₹2 Cr awards |
| CA / pipeline windows | Applications till 31.12.2030 |
SATAT administered by MoPNG is subsumed from 1 September 2026 under the Assured Offtake Mechanism. Committed liabilities incurred under SATAT prior to GOBARdhan notification continue to be borne and discharged. Existing SATAT ROs are encouraged to integrate under GOBARdhan.
Under the guidelines, the Synchro Operator (GAIL) is responsible for payment to CBG producers under the Pricing Framework and is a party to every Tripartite Agreement.
Projects predominantly based on MSW/sewage where at least 50% of feedstock for CBG is from MSW/sewage are excluded from Capital Assistance and from CGSCBG coverage under these guidelines.
CGSCBG covers greenfield projects. Standalone biogas upgradation and capacity enhancement projects are listed as not eligible for guarantee cover.
This OM cites IS 16087:2025 for biomethane, plus the applicable PNGRB Access Code regulations depending on trunk, CGD or cascade retail-outlet delivery.
Read the full 78-page component-wise operational guidelines. This webpage is an explainer only.
F. No. L-16022/9/2025-GP-I-Part(1) (E:57024) · Kartavya Bhawan-03, New Delhi · Dated 15 September 2026.BIOPOWER – BPG Renewables Pvt. Ltd. (Synod Group) helps with feedstock/evacuation diligence, DPR, offtake pathway design and EPC with SCADA/quality compliance from the start.